SECTION 8
PROSECUTION AND PROGRESS
79
No contract adjustment will be allowed under the provisions specified in
this section to the extent that performance would have been suspended or
delayed by any other cause, or for which an adjustment is provided for or
excluded under any term or condition of this contract.
Any contract adjustment warranted due to suspension of work ordered by
the Engineer will be made in the same manner as provided for right of way
delays in Section 8-1.09, "Right of Way Delays."
• In the event of a suspension of work under any of the conditions set forth in
this Section 8-1.05, the suspension of work shall not relieve the Contractor of the
responsibilities as set forth in Section 7, "Legal Relations and Responsibility."
8-1.06 TIME OF COMPLETION
• The Contractor shall complete all or any designated portion of the work called
for under the contract in all parts and requirements within the time set forth in the
special provisions.
• A working day is defined as any day, except as follows:
(a) Saturdays, Sundays and legal holidays;
(b) Days on which the Contractor is prevented by inclement weather or
conditions resulting immediately therefrom adverse to the current
controlling operation or operations, as determined by the Engineer, from
proceeding with at least 75 percent of the normal labor and equipment
force engaged on that operation or operations for at least 60 percent of the
total daily time being currently spent on the controlling operation or
operations; or
(c) Days on which the Contractor is prevented, by reason of requirements in
"Maintaining Traffic" of the special provisions, from working on the
controlling operation or operations for at least 60 percent of the total daily
time being currently spent on the controlling operation or operations.
• Should the Contractor prepare to begin work at the regular starting time of any
day on which inclement weather, or the conditions resulting from the weather, or
the condition of the work, prevents the work from beginning at the usual starting
time and the crew is dismissed as a result thereof and the Contractor does not
proceed with at least 75 percent of the normal labor and equipment force engaged
in the current controlling operation or operations for at least 60 percent of the total
daily time being currently spent on the controlling operation or operations, the
Contractor will not be charged for a working day whether or not conditions should
change thereafter during that day and the major portion of the day could be
considered to be suitable for those construction operations.
• The current controlling operation or operations is to be construed to include
any feature of the work (e.g., an operation or activity, or a settlement or curing
period) considered at the time by the Engineer and the Contractor, which, if
delayed or prolonged, will delay the time of completion of the contract.
• Determination that a day is a non-working day by reason of inclement weather
or conditions resulting immediately therefrom, shall be made by the Engineer. The
Contractor will be allowed 15 days from the issuance of the weekly statement of
working days in which to file a written protest setting forth in what respects the
Contractor differs from the Engineer; otherwise, the decision of the Engineer shall



Pages This Set: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sets
: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Home improvement ideas can be frustrating when it comes to kitchen cabinets, swimming pools spas, peace of mind security, patio enclosures sunrooms, vinyl siding, replacement windows, bird bat pest control, and so on. Free Add URL 1, Free Add URL 2, Free Add URL 3, Free Add URL 4, Free Add URL 5, Free Add URL 6
 

ADT Security - Replacement Windows - Home Improvement - Vinyl Siding Cost - Bird Pest Control
Inground Swimming Pools - Custom Kitchen Cabinets - Porch / Patio Enclosures - Add Real Estate URL - Site Map

Copyright © 2004 - 2008 Vinyl Siding Guide by Site-Found Add URL

Business / Companies Home and Garden Home Improvement / Decorating Miscellaneous