SECTION 6
CONTROL OF MATERIALS
37
• If the Contractor elects to obtain material under (1), the use of the site shall be
subject to the terms, conditions and limitations of the arrangement made between
the property owner and the Department, and the Contractor shall pay the charges as
are provided for in the arrangement made by the Department with the property
owner. Deductions will be made from any moneys due or that may become due the
Contractor under the contract sufficient to cover the charges for the material
removed.
• If the Contractor elects to obtain material under (2), the Contractor shall pay
the charges as are provided for in the agreement between the owner and the
Contractor, and deductions will not be made from any moneys due or that may
become due the Contractor under the contract to cover the charges.
• Before acceptance of the contract, the Engineer may require the Contractor to
submit written evidence that the owner of the material source is satisfied that the
Contractor has satisfactorily complied with the provisions of either— (1), the
arrangement between the Department and the owner, or (2), the agreement between
the owner and the Contractor, as the case may be.
• Full compensation for furnishing all labor, materials, tools, equipment, and
incidentals, and for doing all the work involved in furnishing and producing
specified materials from possible local material sources, including the construction
of any access roads or fences and any clearing, grubbing and stripping of material
sources, and all processing of whatever nature and extent required, shall be
considered as included in the price paid for the contract item of work involving the
material and no additional compensation will be allowed therefor.
6-2.03 MANDATORY LOCAL MATERIAL SOURCES
• The Contractor shall perform all work required to obtain and produce
acceptable materials from the mandatory local material sources designated in the
special provisions and shall have no right to obtain the materials from any other
source or sources. As part of the work in producing acceptable materials from the
mandatory sources, it will be necessary for the Contractor to perform certain
processing of the material as set forth in the special provisions. Any processing of
the material required in addition to that specified in the special provisions which, in
the opinion of the Engineer, is necessary to produce acceptable material from the
mandatory sources will be paid for as extra work as provided in Section 4-1.03D.
• If the Engineer determines that the designated mandatory local material source
or sources are no longer to be used because they are exhausted or for other reasons,
the Engineer will designate an alternative mandatory local material source or
sources from which the Contractor shall obtain the balance of the material required.
• In this case the Department will pay the Contractor for the cost of moving the
Contractor's plant to the new mandatory source and erecting the plant as extra work
as provided in Section 4-1.03D. Construction of access roads, fences, clearing and
grubbing or stripping of the new mandatory source, ordered by the Engineer to be
performed, will be paid for as extra work as provided in Section 4-1.03D. The
Department will also allow or deduct, as the case may be, the increase or decrease
in haul cost due to an increase or decrease in the length of haul involved. Increased
haul costs will be paid for as extra work as provided in Section 4-1.03D, and
deductions for decreased haul will be determined in the same manner. No
allowance or additional compensation will be made for lost time or for delay in
completing the work due to moving the Contractor's plant from the designated



Pages This Set: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
Sets
: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Home improvement ideas can be frustrating when it comes to kitchen cabinets, swimming pools spas, peace of mind security, patio enclosures sunrooms, vinyl siding, replacement windows, bird bat pest control, and so on. Free Add URL 1, Free Add URL 2, Free Add URL 3, Free Add URL 4, Free Add URL 5, Free Add URL 6
 

ADT Security - Replacement Windows - Home Improvement - Vinyl Siding Cost - Bird Pest Control
Inground Swimming Pools - Custom Kitchen Cabinets - Porch / Patio Enclosures - Add Real Estate URL - Site Map

Copyright © 2004 - 2008 Vinyl Siding Guide by Site-Found Add URL

Business / Companies Home and Garden Home Improvement / Decorating Miscellaneous