SECTION 6
CONTROL OF MATERIALS
34
events occurring outside of the United States, and it shall be the Contractor's
responsibility to deliver materials obtained from outside of the United States to the
point of entry into the continental United States in sufficient time to permit timely
delivery to the job site.
• The Contractor, at no cost to the State, shall supply the facilities and arrange
for any testing required in California which the State is not equipped to perform.
All testing by the Contractor shall be subject to witnessing by the Engineer.
• The manufacturer, producer or fabricator of foreign material shall furnish to
the Engineer a Certificate of Compliance in conformance with the provisions in
Section 6-1.07, "Certificates of Compliance." In addition, certified mill test reports
clearly identifiable to the lot of material shall be furnished where required in these
specifications or otherwise requested by the Engineer.
• If the welding of steel for structural steel members or the casting and
prestressing of precast prestressed concrete members is to be performed outside of
the United States, the following requirements shall apply:
1. The fabrication shall be performed only within the plants and by
fabricators who have previously established, to the satisfaction of the
Engineer, that they have the experience, knowledge, trained manpower,
quality controls, equipment and other facilities required to produce the
quality and quantity of work required. At the option of the Engineer,
prequalification of the plant and fabricator will be established either by the
submission of detailed written proof thereof or through in-plant inspection
by the Engineer or the Engineer's representative, or both.
2. The Contractor shall make written application to the Engineer for approval
for the foreign fabrication at the earliest possible time and in no case later
than 50 days in advance of the planned start of fabrication. The
application shall list the specific units or portion of a work which will be
fabricated outside of the United States.
3. The Contractor shall advise the Engineer, in writing, at least 20 days in
advance of the actual start of any of the foreign fabrication.
4. All documents pertaining to the contract, including but not limited to,
correspondence, bid documents, working drawings and data shall be
written in the English language and all numerical data shall use the
International System of Units (SI) {United States Standard Measures} for
measurement.
• The use of steel manufactured outside of the United States as unidentified
stock material, as provided in Section 55-2.07, "Unidentified Stock Material," will
not be allowed.
6-1.09 STATE SPECIFICATION NUMBERS
• The State Specification number of material furnished on the contract shall
conform to the number specified in these specifications or the special provisions for
the material involved, except that material conforming to a later specification issue
will be acceptable.



Pages This Set: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49
Sets
: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Home improvement ideas can be frustrating when it comes to kitchen cabinets, swimming pools spas, peace of mind security, patio enclosures sunrooms, vinyl siding, replacement windows, bird bat pest control, and so on. Free Add URL 1, Free Add URL 2, Free Add URL 3, Free Add URL 4, Free Add URL 5, Free Add URL 6
 

ADT Security - Replacement Windows - Home Improvement - Vinyl Siding Cost - Bird Pest Control
Inground Swimming Pools - Custom Kitchen Cabinets - Porch / Patio Enclosures - Add Real Estate URL - Site Map

Copyright © 2004 - 2008 Vinyl Siding Guide by Site-Found Add URL

Business / Companies Home and Garden Home Improvement / Decorating Miscellaneous