SECTION 23 – ASPHALT CONCRETE
TABLE OF CONTENTS
Section
Page
23-1
GENERAL ................................................................................................................ 23.1
23-2
MIX FORMULA AND DESIGN.................................................................................23.1
23-3
AGGREGATE........................................................................................................... 23.1
23-4
RECYCLED ASPHALT PAVEMENT........................................................................ 23.2
23-5
HAULING EQUIPMENT ........................................................................................... 23.3
23-6
NOT USED............................................................................................................... 23.4
23-7
NOT USED............................................................................................................... 23.4
23-8
ASPHALT CONCRETE PLACEMENT METHOD ....................................................23.4
23-8.01
General......................................................................................................... 23.4
23-8.02
Pre-Overlay Preparation............................................................................... 23.5
23-8.03
Spreading ..................................................................................................... 23.6
23-8.03.A
Hand Spreading........................................................................................ 23.6
23-8.03.B
Mechanical Spreading Equipment............................................................23.6
23-8.04
Joints ............................................................................................................ 23.7
23-8.05
Compacting .................................................................................................. 23.7
23-8.05.A
Density requirements - Minor Streets .......................................................23.7
23-8.05.B
Density Requirements - Major Streets......................................................23.7
23-9
ASPHALT CONCRETE PLACEMENT ACCEPTANCE TESTING...........................23.8
23-9.01
Pavement Density Testing............................................................................23.8
23-9.01.A
Lot Sizes................................................................................................... 23.8
23-9.01.B
Laboratory Density ................................................................................... 23.8
23-9.01.C
Core Density............................................................................................. 23.8
23-9.02
Pay Factors ..................................................................................................23.8
23-10
ASPHALT RUBBER HOT MIX-GAP GRADED (ARHM-GG) ...............................23.9
23-10.01
Type 1 Asphalt-Rubber Binder ...................................................................23.10
23-10.02
Type 2 Asphalt-Rubber Binder ...................................................................23.10
23-10.03
Aggregate...................................................................................................23.12
23-10.04
Equipment ..................................................................................................23.12
23-10.04.A
Haulers .................................................................................................23.12
23-10.04.B
Asphalt Heating Tank ...........................................................................23.12
23-10.04.C
Mechanical Blender..............................................................................23.12
23-10.04.D
Storage/Reaction Tank.........................................................................23.13
23-10.04.E
Supply System......................................................................................23.13
23-10.04.F
Temperature Gage ...............................................................................23.13
23-10.05
Placement...................................................................................................23.13
23-11
MEASUREMENT AND PAYMENT.....................................................................23.13



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Swimming Pools by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6