SECTION 17
DUST CONTROL
17-1 GENERAL
Dust control shall consist of applying water or dust palliative to alleviate or prevent dust
nuisance resulting from the Contractor's operations, either within or outside the Work right-of-
way.
Dust control shall be performed by the Contractor at any time dust, resulting from the
Contractor’s operations, becomes a nuisance or visual impediment, or as directed by the
Agency. Failure to adequately control dust will be cause for the Agency to direct the Contractor
to suspend operations or for the Agency to perform such activity with all costs to be borne by
the Contractor.
The application of water for dust control may be performed by the Contractor for the
Contractor’s convenience. Water shall be applied as provided in Section 16, “Water Used in
Construction”, of these Specifications.
17-2 DUST PALLIATIVE
Dust palliative shall be applied when, in the opinion of the Agency, this type of dust control is
required. Dust palliative shall consist of an asphaltic emulsion binder as specified in Section
18-1.02, “Materials”, of the State Specifications. Dust palliative shall be applied as specified in
Section 18-1.03, “Application”, of the State Specifications, or as directed by Agency.
17-3 MEASUREMENT AND PAYMENT
Full compensation for applying water for dust control is included in the prices paid for the
various items of work involved and no additional compensation will be paid.
When asphaltic emulsion binder for dust palliative is to be paid for as an item of work, the
unit of measurement shall be a ton. Quantities of asphaltic emulsion binder for dust palliative to
be paid for will be determined prior to the addition of water as provided in Section 94-1.07,
“Measurement”, of the State Specifications. The price paid per ton for asphaltic emulsion binder
for dust palliative includes full compensation for furnishing all labor, materials, tools, equipment,
and incidentals and for doing all the work involved in adding water, mixing, and applying the
dust palliative as shown or specified in the Contract, as specified in these Specifications, and as
directed by the Agency.
When the Contract does not include a pay item for asphaltic emulsion binder for dust
palliative and the Agency directs the Contractor to apply dust palliative, furnishing and applying
dust palliative will be paid for as extra work as provided in Section 9, “Changes and Claims”, of
these Specifications.



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Replacement Windows by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6