Section 9 – Changes and Claims
12/1/03
9.8
9-14 CONTRACT CHANGE ORDER (CCO)
The Agency will issue a Contract Change Order (CCO) for approval if a change to the Total
Contract Price or Contract Time is necessary. The Contractor shall not be entitled to any
adjustments in either Contract Time or Total Contract Price for changes performed without
written direction from the Agency. Adjustments in Contract Time or Total Contract Price for
changes performed will not be made until a Contract Change Order is approved. A Contract
Change Order is comprised of one or more Field Instructions or other written directives, and
contains a summary of each change and changes to the Contract Time or Total Contract Price.
9-15 ACCEPTANCE OF ORDERS FOR CHANGES
The Contractor’s written agreement of a Contract Change Order, Field Instruction, or other
written directive will constitute his final and binding agreement to the provisions of the Contract
Change Order, Field Instruction, or other written directive, and a waiver of all claims in
connection therewith, whether direct or consequential in nature, including those of any
Subcontractors or suppliers. If the Contractor disagrees with any Contract Change Order, Field
Instruction, or other written directive, the Contractor may submit a notice of potential claim to the
Agency in accordance with Section 9-17, “Notice of Potential Claim”, in this Section of these
Specifications. Disagreement with the provisions of a Change Order, Field Instruction, or other
written directive will not relieve the Contractor of the Contractor’s obligations under the Contract.
9-16 DISPUTE REGARDING CONTRACT REQUIREMENTS
If the Contractor and Agency fail to agree whether or not any work or other matter is within
the scope of the Contract, the Contractor shall nevertheless immediately perform such work
upon receipt of a written Field Instruction or other written directive. Within fourteen (14)
Calendar Days after receipt of the Field Instruction or other written directive, the Contractor may
submit a written protest detailing the Contract requirements exceeded and the approximate cost
and/or time change. Failure to submit a protest within the specified period constitutes a waiver
of the Contractor’s rights to adjustments in the Total Contract Price or Contract Time for the
disputed Contract requirement.
The Contractor shall not stop performing the Work pending resolution of a dispute, unless
ordered in writing by the Agency.
If the Agency agrees with the Contractor’s written protest, the Total Contract Price and/or
Contract Time will be adjusted through a Contract Change Order. Protests and claims denied
by the Agency will be so stated in writing.
9-17 NOTICE OF POTENTIAL CLAIM
The Contractor shall not be entitled to payment of any additional compensation for any
cause, including any disagreement, protest, or change, any act or failure to act by the Agency,
or the happening of any event, thing or occurrence, unless the Contractor has given the Agency
due advance written notice of potential claim as hereinafter specified. The written notice of
potential claim shall set forth the reasons for which the Contractor believes additional
compensation and/or time will or may be due, the nature of the costs and/or time involved, and,
insofar as possible, the amount of the potential claim.
Except as required below, the Contractor shall promptly provide written notification to the
Agency upon discovery of concealed or unknown conditions or any disagreement, protest,
situation, event, or occurrence that may result in a claim. This notice shall be submitted no
more than seven (7) Calendar Days after the discovery or occurrence of any event that may be
the basis for a claim for additional compensation or time; failure to do so waives the claim.



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Replacement Windows by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6