Section 9 – Changes and Claims
12/1/03
9.4
pricing data. Additional requirements for cost and pricing data may also be included in the
Special Provisions. The Agency shall have access to the records supporting such cost and
pricing data in accordance with the following Section (Section 9-7, “Access to Records”).
9-7 ACCESS TO RECORDS
Upon reasonable notice and during normal business hours, the Agency shall have access to
the Contractor’s and Subcontractors’ records for the purpose of verifying and evaluating the
accuracy of cost and pricing data submitted by the Contractor. “Records” as used in this
Section shall include, but not be limited to: original estimates, subcontract agreements,
purchase orders, books, documents, accounting records, papers, project correspondence,
project files, and scheduling information necessary to determine the direct and indirect costs,
job site, area and home office overhead, delay and impact costs. Records shall include the
original Bid and all documents related to the Bid and its preparation, the as-planned
construction schedule and all related documents. Such access shall include the right to
examine and audit such records and make excerpts, transcriptions, and photocopies at the
Agency’s cost.
9-8 PAYMENT FOR CHANGES
The method of payment agreed upon by the Contractor and the Agency, or selected by the
Agency in the absence of agreement, shall be set forth in the order for change.
The three methods of payment are as follows:
9-8.01 Lump Sum Price
The Contractor shall submit a lump sum price proposal. The proposal shall include an
estimate of labor, material, equipment, Subcontractor, and material supplier costs.
The proposal shall include labor surcharges of twenty-six percent (26%), sales tax, and
markups as stipulated in Section 9-9, “Markups for Changed Work”, in this Section of these
Specifications.
9-8.02 Unit Prices
If payment for Contract work is based on unit prices, payment for changed work will be
made based on actual quantities of work done at the unit prices contained in the Contract or unit
prices otherwise agreed upon by the Agency and Contractor if none are contained in the
Contract. Payment for changed work based on Contract or agreed upon unit prices includes the
full cost of the item of work including profit and overhead; and no additional payment or
adjustment will be allowed. If the final quantity of any item of work required under the Contract
varies from the Engineer’s Estimate by twenty-five percent (25%) or more, compensation will be
adjusted in accordance with State Specification Section 4-1.03B, “Increased or Decreased
Quantities”.
9-8.03 Force Account
In the absence of either an agreed lump sum price or unit prices for the change, the Agency
may direct the Contractor to proceed with the changed work on a force account basis. The
Contractor shall keep and present, in a form acceptable to the Agency, a complete and correct
accounting of all costs associated with the change, including all pay records, vouchers,
invoices, etc. The Contractor will be paid for labor, materials, and equipment actually used
during the performance of the changed work as specified in this Section of these Specifications
in Sections 9-8.03.A, “Labor”, 9-8.03.B, “Materials”, and 9-8.03.C, “Equipment”; plus the
percentages stipulated in Section 9-9, “Markups for Changed Work”.
To facilitate agreement on direct craft labor hours, construction equipment hours, and
material quantities, the Contractor shall notify the Agency not less than four (4) hours prior to



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Replacement Windows by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6