Section 9 – Changes and Claims
12/1/03
9.3
The Agency’s written approval of the CICP is required. If the CICP is rejected, the Contractor
shall not appeal the decision.
9-3.05 Sharing Provisions and Formula
Upon acceptance of the CICP, the Contractor will receive fifty percent (50%) of the Net
Capital Savings based on the following formula:
Net Capital Savings = Contract Cost Prior to CICP - (Revised Contract Cost After
CICP + CICP Development Cost + CICP Implementation Cost)
The Contractor's development cost is limited to that directly associated with the preparation
of the CICP package. Development costs will be reimbursed after approval. However, the
Agency will reject costs that cannot be satisfactorily substantiated.
The CICP implementation costs include, when appropriate, engineering costs for reviewing
and redesigning the changes. However, Agency costs for processing the CICP are excluded.
9-4 CHANGES TO THE CONTRACT
If directed by the Agency, within fourteen (14) Calendar Days of issuance of an order for a
change, the Contractor shall provide a cost and time proposal prepared in accordance with the
requirements of Sections 9-8, “Payment for Changes”, and 9-12, “Time Extensions for
Changes”, in this Section of these Specifications. The Contractor’s proposal shall indicate the
amount to be added or deducted from the Total Contract Price, supported by complete details of
all Contractor, Subcontractor, vendor or supplier costs per Section 9-6, “Cost and Pricing Data”,
in this Section of these Specifications. In the event the Agency, for whatever reason, opts to not
proceed with the change, the Agency will reimburse the Contractor for the actual costs
associated with the preparation of the proposal. Contractor shall submit an invoice prepared in
accordance with Section 9-8.03 of these Specifications.
If the Contractor does not submit a proposal within fourteen (14) Calendar Days, and unless
the Agency is otherwise notified within fourteen (14) Calendar Days of a potential cost impact,
the Contractor agrees to perform the work described in the order for change with no additional
compensation. If the order for change is issued on a force account basis, the Contractor must
immediately begin keeping records in accordance with Section 9-8.03, “Force Account”, in this
Section of these Specifications.
9-5 PROSECUTION OF CHANGES TO THE CONTRACT
The Contractor shall comply with and prosecute all portions of the order for change with the
same diligence and manner as if the changes were originally included in the Contract, except as
otherwise provided in the order.
If agreement is reached regarding payment, but not a time adjustment, the Agency shall
have the right to direct the Contractor to proceed with the change at the agreed price. The
impact of the changed work on the project schedule will be considered by the Agency in
accordance with Section 9-12, “Time Extensions for Changes”, in this Section of these
Specifications.
When the Agency and Contractor cannot agree on the credit for deleted work, the Agency’s
estimate will be deducted from the Total Contract Price, unless the Contractor presents proof
prior to the Final Payment that the Agency’s estimate is in error.
9-6 COST AND PRICING DATA
Cost and pricing data submitted by the Contractor shall be true, complete, accurate, and
current. The Agency may require a formal certification to verify Contractor-submitted cost and



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Replacement Windows by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6