Section 8 – Measurement and Payment
07/24/01
8.5
Any violation or non-compliance with Contractor’s legal responsibilities (see Section
6, “Legal Relations and Responsibilities”, of these Specifications), including
withholds for wages adjustments in accordance with California Labor Code Section
1727 and any fines incurred by the Agency as a result of the Contractor’s actions.
When, under the provisions of the Contract, the Agency charges any sum of money against
the Contractor, the Agency will deduct and retain the amount of such charge from a Progress or
Final Payment. If, on completion or termination of the Contract, sums due the Contractor are
insufficient to pay the Agency charges against the Contractor, the Agency has the right to
recover the balance from the Contractor or the Contractor's surety.
8-9 DEDUCTIONS FOR IMPERFECT WORK
For any portion of the Work retained in accordance with Section 5-19, “Right to Retain
Imperfect Work”, of these Specifications, the Agency will deduct from a Progress Payment a just
and reasonable amount.
8-10 LIQUIDATED DAMAGES FOR DELAY
All parties to the Contract agree that time is of the essence, and that the Work shall be
completed within the time stated in the Special Provisions, plus any time extensions as provided
in Section 7-18, “Extension of Time”, of these Specifications. The Contractor’s failure to
complete the Work within the time allowed will result in damages to the Agency. Because it is
impracticable to determine the actual amount of damage by reason of such delay, the
Contractor agrees that the sum(s) set forth in the Special Provisions is (are) a reasonable
amount to be charged for liquidated damages. It is agreed that the Contractor shall pay to the
Agency the sum set forth in the Special Provisions for each and every day’s delay beyond the
time prescribed in the Contract, and the Contractor further agrees that the Agency may deduct
and retain the amount thereof from any monies due or to become due the Contractor under the
Contract.
8-11 FINAL ESTIMATE AND PAYMENT
Subsequent to Field Acceptance as detailed in Section 7-21, “Final Inspection and Field
Acceptance”, of these Specifications, the Contractor shall provide a proposed Final Payment
request, segregated as to Contract item and Contract Change Order work.
The Agency will review the proposed Final Payment request and, after deducting all
previous payments and all amounts to be deducted, withheld, and/or retained under the
provisions of the Contract and Public Contract Code Section 7107, shall create the Final
Payment request. All Progress Payments shall be subject to correction in the Final Payment.
Within fifteen (15) Calendar Days after the proposed Final Payment request is returned to
the Contractor, the Contractor shall submit to the Agency a written approval of said request or a
written statement of exceptions. The Contractor’s statement of exceptions shall be in sufficient
detail for the Agency to ascertain the basis and amount of the exceptions; failure to provide the
detail shall be sufficient cause for denial of the exceptions. Any claim of the Contractor or the
Contractor’s Subcontractors or suppliers with respect to the performance or breach of the
Contract or any alterations thereof (except for payment of the balance of the Contract price as
set forth in the Final Payment request) not specifically set forth in the statement of exceptions, is
waived by the Contractor. If the Contractor fails to file a statement of exceptions within the time
allowed, the Agency will infer acceptance of the final Progress Payment request as submitted to
the Contractor.



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Replacement Windows by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6