Section 8 – Measurement and Payment
07/24/01
8.3
difference between the amount of work actually completed, or materials or equipment furnished,
and the Estimated Quantities for the Allowance.
8-2.06 Payment for Material Not Incorporated in the Work
No Progress Payments will be made for materials and equipment not incorporated in the
Work, unless specifically set forth in the Special Provisions or authorized by the Agency.
8-3 WORK TO BE DONE WITHOUT DIRECT PAYMENT
Compensation for any portion of the Work not specifically identified in the Bid Form or
Schedule of Values is understood to be included in the price for other items, unless specified in
the Special Provisions as extra work. No additional compensation is allowed for additional
shifts or premium pay necessary to ensure that the Work is completed within the time limits
specified in the Contract.
8-4 PAYMENT FOR USE OF COMPLETED PORTIONS OF WORK
If the Agency accepts a completed or partially completed portion of the Work under Section
4-10, “Use of Completed Portions”, of these Specifications, the Contractor will be compensated
in accordance with Sections 8-11, “Final Estimate and Payment”, and 8-12, “Final Payment to
Terminate Liability of Agency”, in this Section of these Specifications. When the Agency
accepts a completed or partially completed portion of the Work, the warranty period for that
portion commences and the Contractor will be relieved of any further maintenance and
protection of that portion. The Contractor will not be relieved of the Contract requirements for
repairing or replacing defective work and materials.
8-5 PROGRESS PAYMENT PROCEDURES
No Progress Payment will be made when, in the judgment of the Agency, the Work is not
proceeding in accordance with the provisions of the Contract or when the total work done since
the last Progress Payment amounts to less than one thousand dollars ($1,000). Unless
otherwise agreed to at the preconstruction meeting or identified in the Special Provisions, on the
20th of each month the Contractor shall submit in writing for Agency review an estimate of the
total amount and value of work done, including that done under approved Change Orders, and
the acceptable materials furnished and incorporated in the work through the 20th day of the
month. The Bid Form or Schedule of Values shall be used to prepare a Progress Payment
request for the items, or portions of items, of the Work completed during the monthly progress
period. After deducting all previous payments, the retention as described in Section 8-7,
“Retention”, in this Section of these Specifications, and other withholdings as specified in the
Contract from the estimated total value, the Agency will pay the Contractor the balance.
The payment of a Progress Payment or the acceptance thereof by the Contractor does not
constitute acceptance of any portion of the Work, and does not reduce the Contractor’s liability
to replace unsatisfactory work, material, or equipment. An inadvertence or error in an approved
Progress Payment request will not release the Contractor or the Contractor's surety from
damages arising from the work covered by the approved payment request or from enforcement
of every provision of the Contract. The Agency has the right to correct any error made in any
Progress Payment.
8-6 INSPECTION AND PROGRESS PAYMENTS NOT A WAIVER OF CONTRACT
PROVISIONS
No inspection, order, measurement, approval modification, payment, acceptance of work or
material (including, but not limited to, acceptance of the entire Work), time extension, or



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Replacement Windows by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6