Section 8 – Measurement and Payment
07/24/01
8.2
the contract item price for mobilization or two and one-half percent (2.5%) of
the Total Contract Price, whichever is less, will be paid for mobilization.
b. When the Progress Payment request is ten percent (10%) or more of the
original Total Contract Price (excluding mobilization), seventy percent (70%)
of the contract item price for mobilization or three and one-half percent
(3.5%) of the Total Contract Price, whichever is less, will be paid for
mobilization.
c. When the Progress Payment request is twenty percent (20%) or more of the
original Total Contract Price (excluding mobilization), ninety percent (90%) of
the contract item price for mobilization or four and one-half percent (4.5%) of
the Total Contract Price, whichever is less, will be paid for mobilization.
d. When the Progress Payment request is fifty percent (50%) or more of the
original Total Contract Price (excluding mobilization), one hundred percent
(100%) of the contract item price for mobilization or five percent (5%) of the
Total Contract Price, whichever is less, will be paid for mobilization.
e. After final acceptance of the Contract, the amount, if any, of the Contract item
price for mobilization in excess of five percent (5%) of the original Total
Contract Price will be included for payment in the final estimate made in
accordance with Section 8-11, “Final Estimate and Payment”, in this Section
of these Specifications.
3. The Agency will not pay additional mobilization compensation for work under a
Contract Change Order. Payment for mobilization shall be subject to retention per
Section 8-7, “Retention”, in this Section of these Specifications.
8-2 SCOPE OF PAYMENT
8-2.01 General
Compensation under the terms of the Contract shall be full payment for the Work, including
loss or damage arising from the nature of the Work, action of the elements, or unforeseen
difficulties encountered during the prosecution of the Work and until its final acceptance; and all
risks connected with the prosecution of the Work.
8-2.02 Unit Price Contract
Progress Payments will be made based on the unit price bid and measured quantities for
work completed, plus work completed on approved Change Orders. For compensation for
alterations in quantities of work, including deviations greater than twenty-five percent (25%), see
Section 9-8.02, “Payment for Changes – Unit Prices”, in these Specifications.
8-2.03 Lump Sum or Job Contract
Progress Payments will be based on the approved Schedule of Values for work completed,
plus work completed on approved Change Orders.
8-2.04 Final Pay Items
An item designated as a Final Pay Item in the Contract shall be paid for as specified in
Section 9-1.015, “Final Pay Items”, of the State Specifications.
8-2.05 Allowances
Allowances may be included in the Bid Form for materials and/or work that may be added
during the course of the Contract. The Allowance may be used in whole, in part, or not at all as
determined by the Agency. Whenever costs of the Work included in the Allowance item are
more or less than the specified Allowance amount, the Total Contract Price will be adjusted
accordingly by Contract Change Order. The Contractor shall make no claim nor receive any
compensation for anticipated profits, loss of profit, damages, or any extra payment due to any



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Replacement Windows by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6