Section 7 – Prosecution of the Work
12/1/03
7.9
7-17 INCLEMENT WEATHER AND CONTRACT TIME
A Contract day on either Working Day or Calendar Day contracts will not be charged if, in
the opinion of the Agency, inclement or unsuitable weather or its effects prevents working on
the current controlling operation at the beginning of the shift for at least five (5) consecutive
hours, or for at least (5) hours during the shift. A current controlling operation is any feature of
the Work (e.g., an operation or activity including settlement, curing periods, and submittal
activities) that if delayed or prolonged will delay the time of completion of the Contract.
7-18 EXTENSION OF TIME
The Contractor will be allowed a time extension to complete the Work equal to the sum of all
unavoidable delays as determined in accordance with Section 7-12.02, “Unavoidable Delays”, in
this Section of these Specifications, plus any adjustments in Contract Time due to Contract
Change Orders as outlined in Section 9-12, “Time Extensions for Changes", in these
Specifications. During such time extension, the Contractor will not be charged for extra
engineering and inspection or liquidated damages. Requests for a time extension must be
submitted in writing to the Agency within ten (10) Calendar Days of the event that is the reason
for the request for time extension and before the expiration of the Contract time.
7-19 SUBSTANTIAL COMPLETION
When the Contractor considers the entire Work, or a specific portion of the Work,
substantially complete, the Contractor shall certify in writing to the Agency that the Work is
substantially complete and request that the Agency grant substantial completion. Within five (5)
Working Days, the Agency and the Contractor shall inspect the Work to determine the status of
completion. If the Agency does not consider the Work ready for its intended use, the Agency
will notify the Contractor in writing, giving the Agency’s reasons. If the Agency considers the
Work ready for its intended use, the Agency will grant substantial completion. The Agency will
provide a list of items to be completed or corrected (punch list) before Final Acceptance and
Final Payment. Within ten (10) Calendar Days of being provided a list of items to be completed
or corrected, the Contractor shall proceed to correct or complete such items. The counting of
time for liquidated damages will cease for the entire Work, or a specific portion of the Work, on
the date substantial completion is granted, but shall not bind the Agency to formal acceptance
nor relieve the Contractor from the responsibility of completing or correcting any work.
7-20 CLEANING UP
Throughout the construction period, the Contractor shall keep the site of the Work in a
presentable condition, dispose of any surplus materials, keep roadways reasonably clear of dirt
and debris, keep all sidewalk and other pedestrian areas clear of dirt, loose gravel, debris and
any tripping hazards, clean out all drainage ditches and structures, and repair any fences or
other property damaged during the progress of the Work, to the satisfaction of the Agency. The
Contractor shall also keep the work site cleaned of all rubbish, excess material, and equipment.
All portions of the work shall be left in a neat and orderly condition prior to requesting final
inspection. Surplus material shall be disposed of in accordance with Section 18-7, “Surplus
Material Disposal”, of these Specifications.
The final inspection will not be made until final clean up has been accomplished.



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Replacement Windows by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6