Section 7 – Prosecution of the Work
12/1/03
7.4
items of work highlighted. A corrective course of action shall also be included when problem
areas or delays are encountered.
All schedule updates or revisions shall show on the critical path the effects of any
occurrence upon which the Contractor has based a notice of potential claim or will base any
claim (see Section 9, “Changes and Claims”, of these Specifications) and shall expressly call
the Agency’s attention to the effects.
7-5.03 Four-Week Rolling Schedule
A four-week rolling schedule shall be provided by the Contractor at each progress meeting.
The schedule shall provide an accurate representation of the work performed the previous week
and work planned for the current week and subsequent two (2) weeks.
The schedule shall be provided in a bar chart form with information derived from and
consistent with the current project schedule. The schedule shall include activity ID number,
activity description, start and finish dates (both scheduled and actual), and any other information
requested by the Agency. Each activity shall be coded to note activities on the critical path and
activities that are behind schedule.
7-5.04 Float
Float in any activity, milestone completion date, and/or Contract completion date is owned
by the Project and, as such, is a resource available to both the Agency and the Contractor.
Neither the Agency nor the Contractor owns the float time.
Unless otherwise provided herein, float is synonymous with total float. Total float is the
period of time measured by the number of Working or Calendar Days (as specified in the
Contract) each non-critical path activity may be delayed before it and its succeeding activities
become part of the critical path. If a non-critical path activity is delayed beyond its float period,
then that activity becomes part of the critical path and controls the end date of the work. Thus,
delay of a non-critical path activity beyond its float period will cause delay to the project itself.
Acceptance of a Baseline Schedule, Monthly Update(s), or Revised Schedule, which is
based on less time than the maximum time allowed for milestone or Contract completion, does
not serve to change any Contract duration, nor does it serve as a waiver of either the
Contractor's or Agency’s right to utilize the full amount of time specified in the Contract. As
such, liability for delay of the project completion date rests with the party actually causing delay
to the project completion date. For example, if Party A uses some, but not all, of the float time
and Party B later uses the remainder of the float time as well as additional time beyond the float
time, Party B shall be liable for the costs associated with the time that represents a delay to the
project's completion date. Party A would not be responsible for any costs since it did not
consume all of the float time and additional float time remained, and the Project or milestone
completion date was unaffected.
7-6 UNUSUAL SITE CONDITIONS
The Contractor shall promptly, and before the following conditions are disturbed, notify the
Agency, in writing, of any:
1. Material that the Contractor believes may be hazardous waste, as defined in Section
25117 of the Health and Safety Code, which is required to be removed to a Class I,
Class II, or Class III disposal site in accordance with provisions of existing law.
2. Subsurface or latent physical conditions at the site differing from those indicated in
the Contract.



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Replacement Windows by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6