Section 7 – Prosecution of the Work
12/1/03
7.3
progress schedule at the preconstruction conference (see Section 7-3, ”Preconstruction
Conference and Progress Meetings”, in this Section of these Specifications). The baseline
progress schedule shall show all major portions of the Work, the estimated dates on which the
Contractor shall start each portion of the Work, and the contemplated dates for completing each
portion of the Work or the approximate percentage of the Work or portions of the Work
scheduled for completion at any time.
Unless agreed to by the Agency, the progress schedule shall be updated and submitted to
the Agency with each Progress Payment request or when requested by the Agency. All
schedule updates or revisions shall show the effects of any occurrence upon which the
Contractor will base a notice of potential claim or has based any claim (see Section 9, “Changes
and Claims”, of these Specifications), and shall expressly call the Agency’s attention to those
effects. A revised or updated schedule shall be submitted within ten (10) Working Days of an
Agency request.
The Contractor shall carry out the various elements of the Work concurrently, as is
practicable, and shall not defer construction of any portion of the Work in favor of any other
portion, without the express written approval of the Agency.
Despite the submission of a progress schedule, the Contractor shall be governed by the
direction of the Agency if, in the judgment of the Agency, it becomes necessary to accelerate
the Work or any part thereof, or cease work at any particular point and concentrate the
Contractor’s forces at such other point or points, with the intent of preventing delays.
7-5.02 CPM Schedule
When required by the Special Provisions, in lieu of the progress schedule required by the
previous Section (Section 7-5.01), the Contractor shall submit a practicable Critical Path Method
(CPM) network schedule within thirty (30) days of receipt of the Contract. Unless otherwise
agreed to by the Agency, the latest version of MS Project or Primavera shall be used. The CPM
network diagram shall be time-scaled and include printouts showing the mathematical analysis
of the CPM network diagram. Activities shall include, but not be limited to, construction
activities, procurement activities, submittal activities, and any other activities by the Contractor,
the Agency, or any other entity that may impact the Work. Submittal and procurement activities
shall include falsework drawings, post tensioning drawings, test procedures, mix designs, long
time lead items, etc. The following information shall be shown for each activity:
1. Unique number(s) for each activity
2. Activity description
3. Activity relationships and dependencies (logic)
4. Activity duration in Working Days
5. Early start, early finish, late start, late finish dates (calendar date, i.e. day, month,
year)
6. Total float, free float
7. For completed activities: actual start dates, actual finish dates, duration, and logic
8. Interim milestone dates and completion dates
9. Detailed list of work contained within each activity
10. Manpower loading for each item of work for unit price contracts
11. Cost loading for each item of work for lump sum contracts
The Contractor shall submit three (3) full-size paper copies and an electronic copy of each
CPM schedule. Updates to the CPM schedule shall be submitted with each Progress Payment
request, when Contract events are changed, or within ten (10) Working Days of an Agency
request. A narrative describing the general status of the Work and addressing any problem
areas or delays shall be submitted with each revision or update, with impacts on critical path



This Section: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Sections
: 1 2 3 4 5 6 7 8 9

Remodeling a home can be costly and frustrating, especially in decor of kitchen cabinets, veneer, bathrooms, vinyl siding, arts / crafts, patio enclosures, replacement windows doors, furniture, swimming pools spa, home security, or other architecture areas. Free Add Site 1, 2, 3, 4, 5, 6, 7
 

ADT Home Security - Replacement Windows - Home Improvement Ideas - Vinyl Siding Prices - Shopping - Bat Pest Control
Swimming Pools / Spa - Kitchen Cabinet Remodeling - Patio Enclosures - Site Map - Add URL Real Estate

Copyright © 2004 - 2008 Home Furniture Improvement by Site-Found

Art / Decor Business / Companies Computers / Accessories Education / Schools Entertainment / Books Health / Environment Home and Garden Home Improvement / Decorating Home Sales / Real Estate Life / Homes Literature / Classics Miscellaneous Recreation / Sports Science / Technology Shopping / Gifts Society / Family Websites / Logos Favorites Add URL 2 3 4 5 6